Viva Station
Installation Of the High voltage power systems and Electrical distribution panels for new addition including 124 Lighting, HVAC system and fire alarm
FEB2021-APR2021
UFT
Installation of the All electrical Devisees together with Data and communication wiring and installation with existing and energized power system
FEB2022-JULY2022
ST paul School
Installation of the All electrical Devisees Replacement of Florescence lighting with LED lighting with Lutron Lighting control
DEC2021- MAR2022
Beer store
Installation of the All electrical Equipment’s, over 120 Light fixture in high ceiling together with Fire alarm Devices and control in 40,000SQF Warehouse